‘Chinese Speed’ Created By HZMB Immersed Tunnel Builders

At 6:30,21th December 2015, with the successful installation of NO.24 element, CCCC tunnel builder finally achieve the target of10 elements installation in 2015,one year ten Elements created a new ‘China Speed’.

In the last year, CCCC tunnel builder fully valued every installation weather window, unceasingly optimized the work flow and risk management, scientific coped various adverse factors like as the typhoon, foundation trench sedimentation, Pearl River estuary large runoff volume, the cold wave and strong wind in winter, further improved the ability of on-site emergence disposal and control, quality and efficient completed the floating and installing work of the 10 immersed tunnel elements.


  • Preview:Race with increasing momentum sediments on foundation trench (2016-04-08)
  • Next:HZMB project immersed tunnel length exceeded 4000 meters (2015-11-21)


  • ICP:05060342-2 | Set Index | Favorite | Web Master
    HongKong-Zhuhai-Macao Bridge www.cccchzmb.com
    Web Support:CCCC Ltd