HZMB project succeed in E21 immersing work

——Apply the third sea-lane for the first time

On 23th September 2015, before the astronomy flood tide, HZMB project first applied the third sea-lane for tunnel element(E21) floating transportation and successfully completed the accurate hydraulic connection in deep-sea.

So far, the immersed tunnel of HZMB project is built to 3645 meters, up to 65% of the length of the total immersed tunnel length.
 


  • Preview:Two-thirds of HZMB immersed tunnel had been finished (2015-11-15)
  • Next:E20 installation finished,HZMB immersed tunnel has arrived more than 60% (2015-08-29)